Discussion :: Time and Work
-
X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?
Answer : Option A
Explanation :
Work done by X in 8 days =\( [\frac { 1 } { 40 } *8]\)=\( \frac { 1 } { 5 } \)
Remaining work =[1-\( \frac { 1 } { 5 } \)]=\( \frac { 4 } { 5 } \)
Now,\( \frac { 4 } { 5 } \)work is done by Y in 16 days.
Whole work will be done by Y in\( [16*\frac { 5} {4 } ]\)=20 days.
X's 1 day's work =\(\frac { 1 } { 40} \)Y's 1 day's work =\(\frac { 1 } { 20} \)
(X + Y)'s 1 day's work =[\(\frac { 1 } { 40} \)+\(\frac { 1 } { 20} \)]=\(\frac { 3 } { 40} \)
Hence, X and Y will together complete the work in\(( \frac { 40 } {3 } )\)=13\( \frac { 1 } { 3 } \)days
Be The First To Comment