Home / Arithmetic Aptitude / Time and Work :: Discussion

Discussion :: Time and Work

  1. A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?
  2. A.
    5 days
    B.
    4 days
    C.
    7 days
    D.
    11 days

    View Answer

    Workspace

    Answer : Option D

    Explanation :

    One day work of A, B and C = 1/24 + 1/30 + 1/40 = 1/10 Work done by A and B together in the last 4 days = 4*(1/24 + 1/30) = 3/10
    Remaining work = 7/10
    The number of days required for this initial work = 7 days.
    The total number of days required = 4 + 7 = 11 days.